(Media Office)
Within the plans of WOC to increase its production capacities in various work sites in the fields and the terminal, and within the works of rehabilitating Al-Dahra field and conducting operational tests for the main station in the field after the damage it was exposed to in the year 2015 The Construction Unit of Engineering Dept. and the construction unit in Al-Dahra field during the past period had replaced of replacing the crude oil Transportation line from BL5-1 station in the east to the main station on the field in the west, with a length of 5,185 km.
Where work was begun on the line on 18, May 2022 and completed on 30, July 2022. The work included drilling, packaging, and welding. The number of pipes used in the project amounted to 461 pipes with a diameter of 12 inches.